PDA Technical Reports are highly valued membership benefits because they offer expert guidance and opinions on important scientific and regulatory topics and are used as essential references by industry and regulatory authorities around the world. These reports include terms which explain the material and enhance the reader’s understanding.
The database presented here includes the glossary terms from all current technical reports. The database is searchable by keyword, topic, or by technical report. Each definition provided includes a link to the source technical report within the PDA Technical Report Portal.
(Please select "All" to restart a filtered Search)
Refine Results
Filter By Technical Report Number
Filter By Technical Report Keyword
Filter By Technical Report Category
Air Removal Test
A test used to evaluate air removal and steam penetration in an empty sterilizer that is used for porous/hard goods load sterilization (e.g., Bowie-Dick Test, DART, Lantor Cube, Browns’ Test). (TR01) (TR 48)
Source:
Chamber Leak Test
A test conducted to evaluate possible air infiltration to the chamber under vacuum. [Synonym: Vacuum Leak Test] (TR1) (TR48)
Source:
Commissioning
A well planned, documented and managed engineering approach to the start-up and transfer of facilities, systems and equipment to the end-user that results in a safe and functional environment that meets established design and user requirement specifications. Commissioning precedes Qualification and includes three phases:
1. Inspection, testing, and regulation
2. Adjustment and setting of work
3. Functional testing (TR 3)
A prescribed number of activities designed to take equipment and systems from a static, substantially complete state to an operable state. (TR 48)
A well planned, documented, managed engineering approach to the start-up and turnover of facilities, systems, and equipment to the end-user, that results in a safe and functional environment that meets established design requirements and stakeholder expectations.(TR 54) (TR 54-5)
Source:
Decommissioning
A planned and orderly removal of a facility, operation or system from use. (TR48)
The process of retiring equipment/systems/facilities from production use. (TR54-5)
Source:
Good Engineering Practice (GEP)
Documented proven and accepted engineering methods and practices that applied throughout the project life-cycle to deliver solutions that are cost effective, are compliant with regulations and meet the requirements of the user. (TR48)
Those established engineering methods and standards that are applied throughout the lifecycle to deliver appropriate and cost-effective solutions. (TR60) (TR54-5)